OH Consultant
← All SWMS Documents
☀️

Solar System Commissioning SWMS

Safe Work Method Statement covering the key hazards and control measures for solar system commissioning.

⚖️WHS Regulation 2025 & Codes of Practice — legally binding from 1 July 2026 (s26A)
👷Reviewed by certified occupational health and safety professionals
🗺️State-specific variants for all 8 Australian jurisdictions
$149 AUD✓ Instant Download Available

SWMS variants reference your state’s WHS legislation. Instant download after payment.

Solar system commissioning is the final electrical verification stage where a licensed electrical worker energises, tests and hands over a photovoltaic (PV) installation — including DC array isolation testing, polarity checks, insulation resistance, earth continuity, inverter parameter setting, anti-islanding verification and grid connection. The work involves simultaneous exposure to live DC voltages (often 600–1000 V DC at the array), AC supply at the switchboard, and elevated work on roofs or elevated work platforms. Under WHS Regulation 2025 sections 291 and 299, a Safe Work Method Statement is mandatory because commissioning combines High Risk Construction Work (electrical work where there is a risk of electric shock from energised parts, plus work at heights above two metres on most domestic and commercial roofs). The SWMS must be prepared before work commences, consulted on with workers, and kept available for inspection until the work is complete plus two years if a notifiable incident occurs.

Hazards identified

7 hazards covered, sorted by priority.

Live DC voltage at PV array conductors during string testing (typically 600–1000 V DC, cannot be switched off in daylight)HIGH

Electric shock, sustained DC arc burns, cardiac arrhythmia, deep tissue necrosis, potential fatality and notifiable incident under s35 WHS Act

Fall from roof edge or through brittle/skylight roofing during inverter-to-array continuity walk testingHIGH

Fatal or catastrophic injury from fall greater than two metres, triggering SafeWork notification and category one prosecution exposure

DC arc flash on disconnection of energised PV isolator under load (faulty or non-load-break isolator)HIGH

Severe facial and upper-body burns, retinal damage from UV flash, hearing damage from blast overpressure, prolonged medical treatment

Back-energisation from inverter during grid-tie commissioning before anti-islanding verificationHIGH

Unexpected re-energisation of supposedly isolated conductors causing electric shock to electrician or downstream network worker, breach of AS 4777.2

Working in extreme heat on metal roof during midday irradiance peak required for accurate commissioning readingsMEDIUM

Heat stress, dehydration, contact burns from roof surfaces exceeding 70°C, impaired judgement leading to secondary electrical or fall incident

Incorrect polarity or cross-string wiring discovered only at energisationMEDIUM

Inverter fault, fire ignition in DC combiner, asset destruction and potential structural fire requiring Fire Rescue response and insurer notification

Manual handling of inverters and battery modules (often 25–60 kg) at height or in confined ceiling/garage spacesMEDIUM

Acute musculoskeletal injury, hernia, crush injury to hands and feet, workers compensation claim and lost time injury

Control measures

Hierarchy-of-controls order: elimination → substitution → isolation → engineering → administrative → PPE.

  1. 1Elimination — Where feasible, complete all string polarity, insulation resistance and continuity testing on the ground before modules are connected into series strings to eliminate live DC exposure at height.
  2. 2Elimination — Cover array with opaque tarpaulins during pre-energisation inspection to reduce open-circuit voltage to near-zero, removing live DC hazard during physical handling of conductors.
  3. 3Substitution — Use a CAT IV 1500 V rated insulation resistance tester and PV-specific multimeter (e.g. Seaward PV200 or equivalent) instead of standard electrician's multimeters not rated for DC fault currents.
  4. 4Substitution — Specify and install load-break rated DC isolators compliant with AS 60947-3 in lieu of legacy non-load-break devices to permit safe under-load disconnection.
  5. 5Engineering — Install permanent roof anchor points certified to AS/NZS 5532 prior to commissioning and connect twin-lanyard harness compliant with AS/NZS 1891.1 with shock absorber to nominated anchor.
  6. 6Engineering — Use insulated tools rated to 1000 V per IEC 60900, finger-proof DC connectors (MC4 locking type) and lockout-tagout devices on AC main switch and DC isolators per AS/NZS 4836.
  7. 7Administrative — Conduct documented pre-start briefing using this SWMS, verify electrical licence and CEC accreditation of all workers, and schedule commissioning outside peak irradiance and ambient temperatures above 35°C where practicable.
  8. 8Administrative — Apply a permit-to-energise system requiring two-person verification of polarity, voltage and earth continuity readings against AS/NZS 5033 checklist before closing the DC isolator.
  9. 9PPE — Wear arc-rated coveralls minimum ATPV 8 cal/cm², Class 0 insulated gloves with leather over-gloves tested within the last six months, arc-rated face shield and AS/NZS 1337 safety glasses during energisation.
  10. 10PPE — Non-conductive Class E hard hat to AS/NZS 1801, AS/NZS 2210.3 safety footwear with electrical hazard rating, and high-visibility long sleeves to mitigate UV and incidental contact burns.

Applicable Codes of Practice

AS/NZS 5033:2021 Installation and safety requirements for photovoltaic (PV) arrays⚖ Legally binding · 1 Jul 2026

Mandates commissioning test sequence, DC isolator placement, string voltage limits and signage — the primary technical standard governing this SWMS.

AS/NZS 3000:2018 Electrical installations (Wiring Rules)⚖ Legally binding · 1 Jul 2026

Sets verification, testing and certification duties for the AC side of the installation and supply mains connection at the switchboard.

AS/NZS 4777.2:2020 Grid connection of energy systems via inverters — Inverter requirements

Governs anti-islanding, frequency and voltage settings the commissioning electrician must verify and record before final grid energisation.

Managing the Risk of Falls at Workplaces Code of Practice 2024⚖ Legally binding · 1 Jul 2026

Requires fall prevention controls for any work at height greater than two metres including roof-mounted PV commissioning activities and anchor inspections.

High-Risk Construction Work triggered

3
Construction work carried out at a height of two metres or more

Commissioning requires physical inspection, connector verification and isolator operation at the rooftop array, almost always exceeding two metres above ground level.

14
Construction work involving energised electrical installations or services

Commissioning by definition involves energising the PV array and connecting it to the energised grid supply, with unavoidable exposure to live DC and AC conductors.

Legal consequence

The PCBU must prepare, consult workers on, and keep this SWMS available for inspection; failure exposes officers to Category 1 or 2 offences with penalties that are substantial and indexed annually under the prevailing WHS schedule.

Who this is for

  • CEC-accredited solar installers and designers on residential rooftops
  • Licensed electrical contractors commissioning commercial PV systems
  • Principal contractors managing renewable energy construction projects
  • Solar retailer technical managers overseeing subcontracted commissioning crews

What you receive

  • Editable DOCX template — Microsoft Word compatible
  • State-specific WHS legislation schedule (NSW/VIC/QLD/SA/WA/TAS/NT/ACT)
  • Hazard register with risk ratings + hierarchy-of-control mapping
  • Worker sign-on register, pre-start checklist, and incident escalation flow

Worked example

On a 99 kW commercial rooftop PV commissioning job at a regional distribution warehouse, the lead electrician opens the day with a pre-start huddle on the loading dock and walks the two-person crew through this SWMS. Reviewing the hazard register, the apprentice flags that the southern array sits within 1.2 m of an unprotected skylight — not noted on the original install JSA. The team consults the controls section, escalates from administrative exclusion zoning to engineering control, and installs temporary skylight mesh covers before any roof access. Each worker signs the SWMS sign-on sheet, confirming current electrical licence numbers, harness inspection dates and Class 0 glove test certificates. During string testing the insulation resistance reading on String 7 returns 0.4 MΩ — below the AS/NZS 5033 threshold. Rather than energising, the supervisor pauses work, re-opens the SWMS, applies the lockout-tagout administrative control, tarps the affected string to drop Voc, and isolates a damaged MC4 connector chafed against a roof penetration. The fix is documented as a SWMS amendment in the site diary, the crew re-briefs on the change, signs the amendment column, and only then proceeds to grid energisation and AS/NZS 4777.2 anti-islanding verification with the inverter.

Related legislation

  • WHS Act 2011 (model)
  • WHS Regulation 2025
  • AS/NZS 3000 — Electrical installations
What's in this SWMS

Document details

Regulation
WHS Regulation 2025
HRCW Category
Electrical work — PV array commissioning on roof (risk of fall > 2 m)
Hazards Identified
9 hazards with controls
Format
Editable DOCX (Microsoft Word)
Author
Certified Industrial Hygienist (CIH)
Delivery
Instant download after payment