High-level dust and cobweb removal covers cleaning of overhead structures, beams, light fittings, ductwork, rafters and atrium ceilings in warehouses, factories, places of worship and large public buildings. The work routinely requires elevated work platforms (EWPs), scissor lifts, podium ladders or extension-pole systems operated from ground level, and exposes workers to accumulated nuisance dust, insulation fibres, bird droppings, dead insects and dislodged debris falling into the eye and breathing zone. Because the task involves work at height above two metres and frequently occurs in occupied or partially occupied facilities, it is captured by WHS Regulation 2025 Schedule 1 as High Risk Construction Work, mandating a Safe Work Method Statement before work commences. The SWMS must be prepared in consultation with workers, signed on by every operative, kept on site for the duration of the activity and retained for at least two years (or the life of any incident investigation), satisfying the PCBU's primary duty of care under section 19 of the WHS Act.
Hazards identified
7 hazards covered, sorted by priority.
Serious head, spinal or pelvic injury; fatality from ejection or tip-over; coronial inquest and Category 1 prosecution exposure
Acute respiratory irritation, occupational asthma, zoonotic infection, long-term silicosis-pattern lung disease and notifiable occupational illness
Head laceration, eye penetration injury, mercury exposure from broken tubes, public liability claim from struck bystanders
Corneal abrasion, conjunctivitis, foreign body embedment requiring ophthalmic removal and lost-time injury
Electrocution, arc flash burns, cardiac arrest; breach of WHS Reg 2025 Part 4.7 electrical safety duties
Structural damage, accidental sprinkler activation flooding stock, operator crush injury between basket and overhead obstruction
Rotator cuff impingement, cervical strain, chronic shoulder injury and workers compensation claim under state scheme
Control measures
Hierarchy-of-controls order: elimination β substitution β isolation β engineering β administrative β PPE.
- 1Elimination β Where possible, perform cleaning during scheduled shutdowns from permanent maintenance walkways or catwalks fitted with compliant guardrails, removing the need for elevated access entirely.
- 2Elimination β Schedule work outside occupied hours to eliminate exposure of building occupants, customers or congregants to falling debris and airborne contaminants.
- 3Substitution β Replace traditional feather dusters with HEPA-filtered backpack vacuums fitted with extension wands, capturing dust at source rather than dispersing it into the breathing zone.
- 4Substitution β Use telescopic carbon-fibre poles (lighter, under 2 kg) in place of aluminium extension poles to reduce overhead musculoskeletal loading per AS/NZS ISO 11228.1.
- 5Engineering β Operate EWPs compliant with AS 2550.10 with daily pre-start logbook checks, harness anchor points, and overload sensors; isolate and lock out electrical circuits to overhead fittings per AS/NZS 4836.
- 6Engineering β Establish a 3 m exclusion zone beneath the work area using bollards, hi-vis bunting and signage to prevent falling-object strikes per AS 1742.3.
- 7Administrative β Conduct documented pre-start briefing using this SWMS, verify EWP operator Licence to Perform High Risk Work (WP class), and rotate operatives every 45 minutes to manage fatigue.
- 8Administrative β Implement a permit-to-work system for any cleaning within 600 mm of energised electrical fittings; confirm de-energisation and test-before-touch per AS/NZS 4836.
- 9PPE β Issue P2 disposable respirators (AS/NZS 1716) for nuisance dust or full-face P3 powered air-purifying respirators where bird droppings or rodent residue is present.
- 10PPE β Mandate wrap-around safety eyewear to AS/NZS 1337.1, cut-resistant gloves, long sleeves, and a full-body harness with shock-absorbing lanyard to AS/NZS 1891.1 attached to the EWP basket anchor.
Applicable Codes of Practice
Mandates hierarchy of fall controls for any work above 2 m, directly governing EWP selection, harness use and fall-arrest anchorage on this task.
Prescribes daily pre-start inspection, ground assessment, operator competency and safe operating procedures for the EWP used to access high-level surfaces.
Determines correct respirator class (P2 or P3 PAPR) based on contaminant assessment of accumulated dust, droppings and insulation fibre disturbed during cleaning.
Establishes the legal requirement to apply hierarchy of controls and consult workers when preparing this SWMS under WHS Reg 2025 s38.
High-Risk Construction Work triggered
Cleaning beams, atrium ceilings and high-bay light fittings places the worker in an EWP basket or on a podium consistently above 2 m, triggering Schedule 1 cat 9.
EWP and scissor-lift travel through warehouse aisles alongside forklift and pallet-jack movement creates plant-interaction risk captured by the category.
PCBU must prepare, consult on and provide this SWMS before work starts, monitor compliance, and retain it for two years; penalties are substantial and indexed, with current maximums following the prevailing WHS schedule.
Who this is for
- βCommercial cleaning contractors servicing warehouses and distribution centres
- βFacility managers of churches, cathedrals and heritage atriums
- βIndustrial high-level cleaning specialists operating EWP fleets
- βBuilding service contractors quoting periodic deep-clean scopes
What you receive
- βEditable DOCX template β Microsoft Word compatible
- βState-specific WHS legislation schedule (NSW/VIC/QLD/SA/WA/TAS/NT/ACT)
- βHazard register with risk ratings + hierarchy-of-control mapping
- βWorker sign-on register, pre-start checklist, and incident escalation flow
Worked example
A two-person crew is engaged to clean accumulated dust and cobwebs from the 9-metre exposed steel trusses of a regional distribution warehouse during a Sunday shutdown. At 06:30 the supervisor opens this SWMS at the tailgate of the ute and walks the operative through each identified hazard, pausing on the falling-objects line item after noticing fragmented fluorescent diffusers overhead β they jointly decide to upgrade from safety glasses to a full-face shield and add a 3 m bunted exclusion zone beneath the work path, annotating the change directly on the SWMS site-specific amendments page. The EWP operator presents her WP Licence to Perform High Risk Work, completes the AS 2550.10 pre-start logbook, and confirms the warehouse electrician has isolated and locked out the high-bay lighting circuit. Both workers sign the SWMS sign-on register before donning P2 respirators, AS/NZS 1891.1 harnesses clipped to the basket anchor, and cut-resistant gloves. Mid-task at 09:15 the operative notices pigeon droppings concentrated on one truss β recognising the zoonotic trigger flagged in the SWMS hazard register, she descends, the crew upgrades to P3 PAPR respirators stored in the van for exactly this contingency, and the upgrade is recorded as a dynamic risk reassessment on the SWMS continuation sheet before resuming work.
Related legislation
- WHS Act 2011 (model)
- WHS Regulation 2025